Case study 02 · Nuclear marine works

Five times the output on a critical-path task

Every concrete segment lining the cooling-water tunnels is bolted in place, and every bolt pocket then has to be filled by hand. At the original rate the work would have run for months on the critical path. By removing waiting and extra processing, the team went from around 6,000 pockets a month to 30,000.

Download the PDF About the programme
At a glance
5× monthly output, from about 6,000 pockets to 30,000
17 weeks taken off the programme
£2.1m in benefits captured
Bolt pockets filled per month rose from 6,000 to 30,000 after two improvements: pre-wetting by the previous shift and a spray-on curing compound
Context

The challenge

Bolt pocket infilling is repetitive, manual work: remove the temporary bolt, prepare and wet the pocket, fill it with mortar and let it cure. With more than 127,000 pockets still to fill, it sat squarely on the critical path.

The team was averaging about 1,500 pockets a week. At that rate, finishing would have taken months longer than the programme allowed.

Our approach

How we tackled it

We mapped the process step by step, classifying each step as value-adding, value-enabling or non-value-adding. Two sources of waste stood out.

Waiting: pre-wetting moved to the previous shift

Each pocket must be wetted for two hours before filling to meet the manufacturer’s specification. Only two to four people were needed for this, so the rest of the finishers waited. Now the previous shift removes bolts, cleans and pre-wets the pockets, so the next shift starts filling straight away. That recovered 112 working hours a week for an eight-person team and filled 1,120 more pockets a week.

Extra processing: a spray-on curing compound

Every filled pocket was covered with plastic sheet and taped down to help it cure, then uncovered later. A curing compound does the same job with nothing to fit or remove. Across the remaining 127,000 pockets that saves 51.8 days of labour and gains 120 value-adding hours a week.

Outcome

The results

  • Monthly output rose from about 6,000 pockets to 30,000, a 400% gain in efficiency.
  • The bolt pocket programme came down by 17 weeks.
  • £2.1m in benefits captured, including a forecast £1.4m from the shorter programme.
  • 24 miles of masking tape and 2,430 m² of plastic sheet no longer bought, fitted or thrown away.
Nuclear marine works

More from this programme

Case study 03 · Tunnel segment preparation

92% faster segment preparation, with 2.5 million litres of water saved

Challenging the method and the specification cut segment cleaning from 50 minutes to 4, saved 2.5 million litres of water and removed a step altogether.

Read the case study
Case study 04 · Lifting efficiency review

Getting more from a 104-person lifting operation, safely

An efficiency review of a large lifting operation found up to £4.6m a year of efficiency opportunity, all within the client’s own lifting standard.

Read the case study
Case study 05 · Tunnel handover

Learning from one tunnel to de-risk the next

A structured lessons-learned review turned one tunnel handover into a plan to deliver the next, more complex one inside a fixed window.

Read the case study
Start a conversation

Work on the critical path that could flow better?

We help construction and manufacturing organisations find and remove the waste that slows delivery, at any scale. Let’s talk about where yours is.

Book a discovery call Download the case studies